A kitchen has more trades per square foot than any other room in the house. The order they arrive in is not a matter of taste. Each step either covers up the one before it or depends on it for a measurement, and a contractor who lets the order slip pays for it twice, usually with your money.
Before anyone picks up a pry bar
Three things should be settled while the old kitchen is still standing.
Permits. In Oregon, cabinets, countertops, tile and paint do not need a building permit. Moving or removing a wall does. So does cutting a new window or door opening, running new wiring or adding outlets, and altering piping inside walls or under floors, according to the Oregon Building Codes Division. A kitchen that keeps its layout and swaps finishes may need nothing. Move the sink to an island and you are into plumbing, electrical and probably mechanical permits for the range hood duct. The contractor doing the work should be the one pulling them.
Asbestos. Oregon requires an asbestos survey by an accredited inspector before renovation of any residential building constructed before January 1, 2004. The Department of Environmental Quality uses a kitchen remodel as its own example of a partial renovation: the survey covers that area of the structure only (DEQ survey fact sheet). Old sheet vinyl and the black mastic under it are the usual suspects. An owner-occupant doing the work personally is exempt from the survey rule, but a hired contractor is not.
Lead. If the house was built before 1978, any firm paid to disturb more than six square feet of painted surface in a room has to be certified under the federal Renovation, Repair and Painting rule (EPA). Pulling out painted cabinets and a soffit will usually clear that bar.
Order the cabinets and the long-wait appliances now. Nothing else on the job has a delivery date you cannot control.
The order on site
| Stage | What happens | What it waits on |
|---|---|---|
| 1. Protection and demolition | Floors covered, dust walls up, old cabinets, tops, flooring and any soffits out | Asbestos results and lead-safe setup where they apply |
| 2. Framing | Walls moved, openings cut, blocking installed for cabinets and shelves | Structural plan and permit if a wall is involved |
| 3. Rough plumbing | Drains, vents, supply lines, gas line for the range | Final sink, dishwasher and range locations |
| 4. Ductwork | Range hood duct to the outside, any heating runs moved | Hood model and its duct size |
| 5. Rough electrical | Circuits, boxes, lighting cans, under-cabinet feeds | Cabinet shop drawings and appliance specs |
| 6. Rough inspections | Inspector signs off framing, plumbing, mechanical and electrical | The building department's calendar |
| 7. Insulation and drywall | Walls closed, taped, primed | Signed rough inspections |
| 8. Flooring | Site-finished wood or tile goes down before cabinets | Dry, flat subfloor |
| 9. Cabinets | Bases leveled and screwed off, then uppers | Delivery |
| 10. Countertops | Template, fabrication, install | Base cabinets fixed in place; sink and faucet on site |
| 11. Backsplash tile | Tile set to the finished countertop | Countertops in |
| 12. Finish trades | Sink, faucet, disposal, appliances, devices, lights, paint touch-up | Everything above |
| 13. Final inspection | Permits closed | All finish work complete |
Why plumbing goes before wiring
Drain lines have to slope, and they are large and stiff. Ducts are larger still. Wire bends around anything. So the trades with the least freedom go first and the electrician threads through what is left. Reverse the order and somebody ends up drilling a drain-sized hole beside a bundle of cable.
The inspection you cannot skip past
Rough-in work has to be seen before it is covered. Washington's Department of Labor & Industries tells homeowners to make sure the contractor requests inspections before work is covered up (L&I Hire Smart), and the same holds in Oregon. If drywall is going up and you have not seen a signed inspection card, stop the job and ask. Opening a finished wall for an inspector costs far more than a day's wait.
In Oregon the permit and approved plans must be on site for the inspector, and a permit expires if work is suspended or abandoned for 180 days or more (Building Codes Division). A kitchen that stalls for a season over a back-ordered range can lose its permit without anyone noticing.
Floor before cabinets, or after?
Our preference is flooring first for site-finished hardwood and tile, run wall to wall. The cabinets then sit on a continuous floor, the dishwasher slides out without a lip to climb, and a future owner can change the layout without patching. Floating floors are the exception. They need room to move and should not be pinned under a row of loaded cabinets, so they go in after the boxes are set.
The countertop gap
A fabricator will not template stone until the base cabinets are installed, level and fastened, with the actual sink and faucet on hand. Then the slab has to be cut and polished. During that stretch the kitchen has cabinets and no sink. Ask the fabricator for the turnaround in writing before you sign, and ask your contractor to set a temporary plywood top with the old sink if the wait runs long. It is a small job and it keeps the household running.
Paying along the way
Tie payments to stages in the table above. L&I's advice is to pay for completed phases and not by calendar date, and to hold something back until you are satisfied (Hire Smart). Passed rough inspections, cabinets installed and countertops installed are all clean milestones that anyone can verify by looking. More on that in how much to pay a contractor up front.
Questions clients ask about kitchen schedules
Can cabinets be installed before the rough inspection?
No. Cabinets cover the walls the inspector needs to see, and drywall cannot go up until framing, plumbing, mechanical and electrical rough-ins are signed off. Cabinets come after drywall and, for most floor types, after flooring.
Does replacing kitchen cabinets and countertops need a permit in Oregon?
Not by itself. The Oregon Building Codes Division lists cabinets, countertops, tile and similar finish work as exempt from a building permit. New wiring, altered piping inside walls, a new exhaust duct or a moved wall each bring their own permit.
Why does the contractor want the sink and faucet delivered so early?
The countertop fabricator cuts the sink opening and drills the faucet holes from the actual fixtures. If they are not on site at template time, the template waits, and so does everything after it.