What the regulators say
None of the consumer guidance from the two states sets a number. It sets a principle and leaves the arithmetic to you and your contract.
Washington's Department of Labor & Industries advises paying a reasonable down payment, paying for completed phases and not by date, and withholding part of the payment until you are satisfied. It suggests milestones you can see, with "foundation is poured" and "roof is on" as its examples, and a receipt for every payment (L&I Hire Smart).
Oregon's Construction Contractors Board is shorter and sharper: never pay the full amount up front, don't pay in cash, and write checks to the contracted business name. Among its warning signs are a request for full payment or a large deposit before work begins, and a request for cash to buy materials (CCB consumer tools). The Board's Consumer Protection Notice adds that a payment schedule should be in the contract, and that you should stick to it and never pay in full before the work is complete (Consumer Protection Notice).
The Federal Trade Commission notes that some states limit how much a contractor can ask for as a down payment, and gives the same closing advice as everyone else: do not make the final payment until the work is done and you are satisfied with it (FTC).
Why a deposit exists at all
A fair deposit covers real costs the contractor carries before your job produces anything you can see: drawings, permit fees, a place on the schedule, and deposits of their own on cabinets, windows or other items made to order. A contractor who asks for nothing up front on a job with custom cabinets is financing your kitchen. One who asks for half is asking you to finance their business.
Special-order materials are the legitimate reason for a larger early payment. Both agencies point to the same safeguard for that case: write the check jointly to the contractor and the supplier, so the money can only go where it was meant to (Oregon lien notice). Ask the contractor to confirm with the bank first, since some banks require both payees present.
Building a draw schedule
A draw schedule splits the price into payments that fall due when defined work is finished. Good milestones share two qualities. You can verify them by walking through the house, and each one is passed by an inspector or leaves something of value fixed in place.
Here is one way to lay out a kitchen remodel. The shares are an illustration of the shape, not a rule from any agency, and yours should follow where the cost falls in your own job.
| Payment falls due when | Illustrative share | What you can check |
|---|---|---|
| Contract signed, permits applied for, cabinets ordered | 10% | Signed contract with notices; cabinet order confirmation |
| Demolition and framing complete | 15% | Walls open, new framing in |
| Rough plumbing, mechanical and electrical pass inspection | 20% | Signed inspection card |
| Drywall finished and flooring down | 15% | Walls primed, floor complete |
| Cabinets installed | 20% | Boxes fixed, doors and drawers on |
| Countertops and tile in, fixtures working | 10% | Run the water, light the range |
| Final inspection passed, punch list done, lien releases received | 10% | Closed permit; releases in hand |
Notice what the last line does. The final payment is held against three things at once: the inspector's sign-off, the small unfinished items, and the paperwork that protects your title. Contractors sometimes resist a meaningful final payment. Hold to it. It is the only part of the price that keeps anyone coming back for a missing cabinet pull.
Dates are not milestones
A schedule that says "one third at start, one third on the first of next month, one third at completion" pays for time passing. If the job stalls, the second payment still falls due. L&I's phrase is the right one: pay for completed phases, not by date. If a contractor's standard contract uses dates, ask to convert them to stages. A contractor confident of the schedule gives up nothing by agreeing.
Each payment is also a lien checkpoint
Every draw you pay passes through your contractor to subcontractors and suppliers, and any of them who goes unpaid can claim a lien on your house. The Oregon lien notice advises getting lien waivers or releases from everyone the contractor is responsible for paying before you hand over a progress payment. Make it routine: releases for the last draw's work come with the request for the next draw. More in how construction liens reach a homeowner.
Larger jobs: bonds beyond the license bond
The bond behind a contractor's license is small next to a large remodel: $25,000 for an Oregon Residential General Contractor and $30,000 for a Washington general. L&I suggests that for a project costing more than $6,000 you consider asking the contractor to post a performance bond for the full value of the project, and the Oregon CCB makes the same suggestion for large projects. A performance bond is written for your job alone. It costs money, the contractor will pass the premium on, and on an addition or a whole-house job it is worth pricing.
Washington's disclosure statement mentions one more tool: withholding a percentage of the contract price, defined in the contract, as retainage (RCW 18.27.114). If you want retainage, it has to be written into the contract before signing. It cannot be invented at the end.
How to pay
- By check or bank transfer to the business name on the contract and the license record. Not cash, and not to an individual's personal name when you hired a company.
- With a receipt or a paid invoice for every payment, as L&I recommends.
- On the milestone, promptly. Paying late is the fastest way to lose a good contractor's attention, and the contract will usually let them stop work.
Questions clients ask
Is there a legal limit on contractor deposits in Oregon or Washington?
The consumer guidance from the Oregon CCB and Washington L&I cited here does not state a percentage limit. L&I advises a reasonable down payment with later payments tied to completed phases, and the CCB warns against large deposits or full payment up front.
Should I pay a contractor in cash for a discount?
No. The Oregon CCB says not to pay in cash and to write checks to the contracted business name, and both agencies list cash-only requests as a warning sign. A check or transfer also gives you proof of payment if there is a dispute.
When should the final payment be made?
After the work is finished, the final inspection has passed, punch list items are done and you have lien releases from the major subcontractors and suppliers. Every agency cited here says not to pay in full until the work is complete and you are satisfied.
Sources
- Washington State Department of Labor & Industries: Hire Smart step by step
- Oregon Construction Contractors Board: Consumer tools
- Oregon Construction Contractors Board: Consumer Protection Notice (ORS 701.330)
- Federal Trade Commission: How to avoid a home improvement scam
- Oregon Construction Contractors Board: Information Notice to Owner About Construction Liens (ORS 87.093)
- Revised Code of Washington 18.27.114: Disclosure statement required