Asbestos went into houses in dozens of products, most of them unremarkable to look at: sheet vinyl, floor tile and the black adhesive under it, textured ceilings, pipe and duct insulation, cement siding. Intact and sealed, these materials are stable. A remodel is the moment they get cut, scraped and broken, and Oregon's environmental agency states plainly that there is no known safe level of exposure (Oregon DEQ). That is why both states put a check ahead of the demolition.
Oregon: the survey rule
The Department of Environmental Quality's rule covers all residential buildings constructed before January 1, 2004. Before any demolition or renovation, an asbestos survey must be done by an accredited inspector, and a copy of the survey report has to be on site for the whole of the work (DEQ survey fact sheet).
The cutoff year surprises people who assume asbestos ended in the 1970s. A 1998 house is inside the rule.
The survey is scoped to the job. For complete demolition or an extensive renovation, the whole building is surveyed. For a partial renovation, and DEQ's own example is a kitchen remodel, a survey is required for that area only. The inspector takes at least one bulk sample of each suspect material for laboratory analysis, and at least three from each area of sprayed or troweled surfacing such as a textured ceiling. There is one alternative to sampling: a material can be presumed to contain asbestos, in which case it has to be handled and disposed of as if it did.
The owner-occupant exemption
An owner-occupant of a single-unit private residence who is personally doing renovation work inside the home is exempt from the survey rule. Read each part of that sentence, because the exemption is narrower than it sounds:
- It is for work you do yourself. Hire a contractor and the survey requirement applies to the job.
- It covers renovation inside the home. It does not apply if the residence is going to be demolished.
- It does not lift the packaging, labeling and disposal rules. Asbestos waste, friable or not, must go in at least two 6-mil plastic bags or equivalent leak-tight packaging with a hazard label, to a disposal facility permitted to accept it.
DEQ recommends that owner-occupants get a survey or send samples to a lab anyway. There is a practical reason on top of the health one: disposal facilities generally want to see a survey report or lab results before they will take renovation waste.
Who may remove what
| Material | Examples DEQ gives | Who may do the abatement |
|---|---|---|
| Friable (easily crumbled) | Sheet vinyl flooring, pipe, duct and boiler insulation, ceiling and wall texture, ceiling panels | DEQ-licensed asbestos abatement contractors; owner-occupants of a single-unit residence, interior projects only |
| Nonfriable (bound in a solid matrix) | Vinyl floor tile, black mastic, cement siding, roofing or paneling | DEQ-licensed abatement contractors; home and property owners; CCB-licensed contractors |
So your general contractor can lawfully take up nonfriable floor tile, with a notification to DEQ filed five days before the work starts. The same contractor cannot scrape a friable textured ceiling. That needs a DEQ-licensed abatement firm, which files its own notice ten days ahead. Build those lead times into the schedule; they are a common reason a demolition date slips.
Washington: the good faith inspection
Washington's rule sits with the Department of Labor & Industries, and it has no year cutoff. Before any construction, renovation, remodeling, maintenance, repair or demolition, the materials that could be disturbed must have a good faith inspection for asbestos, conducted by an accredited inspector such as an AHERA building inspector. L&I notes that even recently built buildings can contain asbestos materials (L&I asbestos page).
The duty falls on the owner first. Homeowners and building owners are responsible for having the inspection done and giving the results to the contractor, and work should not begin until the contractor has them. If the inspection is skipped, or the results are not shared with the workers who could be exposed, both the owner and the contractor can be fined $600 a day, and more if workers are exposed.
There are two ways to meet the rule without sampling everything. The owner may treat the suspect materials as asbestos and have them handled accordingly, or may document that no suspect material will be affected by the work.
Work in a private residence that is not used for commercial purposes is exempt from the general survey requirement. The exemption is for the homeowner's own project. A homeowner who brings in contractors or workers must still give them the relevant information, and contractors and their workers have to be trained and certified to handle asbestos. A material counts as asbestos-containing at more than 1 percent asbestos.
What this means when you hire
Ask every bidder how asbestos will be handled, and expect a real answer. A careful contractor will ask the age of the house, name the materials they are worried about, and either price a survey or tell you to order one before they finalize the bid. A bid that says nothing, on a house with old flooring under the current floor, has left a cost out.
Order the survey early. Results shape the demolition plan, and abatement, if it is needed, has to be booked and noticed before the remodel crew can start. Keep the report with the house papers afterward. The next project, or the next owner, will want it.
Older houses often carry lead paint as well. See the lead-safe renovation rules for pre-1978 homes.
Questions about asbestos and remodeling
Is an asbestos survey required before a kitchen remodel in Oregon?
Yes, if the house was built before January 1, 2004 and a contractor is doing the work. For a partial renovation such as a kitchen, the survey covers that area only. An owner-occupant doing the work personally is exempt but must still follow the disposal rules.
Can my general contractor remove asbestos flooring?
In Oregon, a CCB-licensed contractor may remove nonfriable material such as vinyl floor tile and black mastic, after notifying DEQ five days in advance. Friable material such as sheet vinyl backing or pipe insulation requires a DEQ-licensed abatement contractor.
Does Washington require an asbestos inspection for newer houses?
Washington's rule has no building-age cutoff. L&I requires a good faith inspection of materials that could be disturbed before renovation work, and notes that recently built buildings can contain asbestos.