What is a change order, and how should one be handled?

A change order is a written amendment to your contract that records a change to the original scope, the effect on the price and the signatures of both parties. It should be signed before the changed work is done. Oregon's Construction Contractors Board advises that a contract allow changes only through written change orders signed by contractor and homeowner, and Washington's L&I tells homeowners to avoid verbal changes altogether.

Remodelers Nearby editorial desk. Checked against the sources listed at the foot of the page in November 2026.

Every remodel changes after it starts. A wall comes open and the plumbing is not where the drawing guessed. The tile you chose is discontinued. You stand in the framed room and decide the window should be wider. None of that is a problem. The problem is a change that gets agreed in a doorway, built on Tuesday and argued about when the final invoice arrives.

The definition, from the regulator

Oregon's Construction Contractors Board defines a change order as an amendment to the contract that outlines a change to the original scope of the project. Its guidance continues: any time your contractor makes a change to the contract, get a change order so the change is documented; both parties should sign it, just like a contract; and if it affects the total cost, that belongs on the change order too (CCB Guide to Home Improvement Contracts).

The Board goes a step further in its list of what a well-written contract contains. One item is a requirement that changes be made only through written change orders signed by both parties (CCB consumer tools). If your contract has no such clause, ask for one before you sign. It protects the contractor as much as you.

Washington's Department of Labor & Industries says the same in fewer words: get all changes to materials or scope in writing, and avoid verbal changes (L&I Hire Smart).

Where changes come from

You change your mind

The simplest kind. You add a pantry cabinet, upgrade the faucet or delete the built-in bench. The contractor prices it, you sign or you do not, and the work follows the signature.

The house surprises everyone

Rot under a window, knob-and-tube wiring in a wall that was supposed to be empty, a beam that is two joists short of where it should bear. These are hidden conditions, and a fair contract says in advance how they are handled. L&I's advice is to agree in writing, before work begins, on how cost overruns will be dealt with. Do that and a hidden condition becomes a priced change order instead of a standoff.

An allowance runs over

An allowance, in the CCB's definition, is a line item for a specific fixture or appliance with an estimated cost; if the item costs more than the amount in the contract, the contractor will require you to pay the difference. That difference should arrive as a change order, with the real invoice attached, not as a line you first see at the end. Allowances that were set low to make a bid look attractive are a common source of bad feeling on a job. Check each one against real prices before you sign the contract.

What a proper change order says

The schedule line is the one contractors leave off and the one that matters most on a long job. Six small changes that each add two days turn into a missed completion date that nobody agreed to and nobody can trace.

A worked example

For illustration only: say the contract price for a kitchen is $48,000 and the tile allowance is $1,200. You choose a tile that comes to $1,950, and you ask for a pantry cabinet the plans did not show, priced at $1,150 installed. Change order 1 records the tile overage of $750. Change order 2 records the cabinet at $1,150 and adds the days the cabinet shop needs. The contract total is now $49,900, both orders are signed and dated, and the final invoice holds no surprises because you have already seen every number on it.

Fixed price or time and materials

A change can be priced as a fixed sum or billed as hours and receipts. Fixed is better for you whenever the work can be seen and measured. Time and materials is honest for work nobody can scope until it is opened up, such as chasing rot, but it needs a cap: a not-to-exceed figure written on the change order, with a phone call required before the cap is passed.

When the work cannot wait

A burst pipe at four in the afternoon will not hold for paperwork. For an emergency, a text or email that states the problem, the fix and a rough price, answered with your approval, is a sound stopgap. The formal change order should follow within a day or two while everyone still remembers what was said. Oregon requires the contract itself to be in writing once the price passes $2,000, and the CCB recommends that all agreements and changes be written whatever the amount (Consumer Protection Notice). A paper trail made on a phone still counts as one.

Reading a contractor by their change orders

Ask a prospective contractor to show you a blank change order form at the bid meeting. The ones who run a tidy job will pull it up without hesitation. If the answer is that they keep it informal, expect the final bill to be informal too.

Questions clients ask about change orders

Does a change order have to be in writing?

Oregon's Construction Contractors Board and Washington's L&I both tell homeowners to put every change in writing, signed by both parties. Oregon law requires a written contract above $2,000, and the Board recommends the contract itself require written change orders.

Should I sign a change order before or after the work is done?

Before. A change order is an agreement on scope and price, and it only protects you if it exists when the work starts. In an emergency, approve by text or email and sign the formal version within a day or two.

Can a change order lower the contract price?

Yes. Deleting work or choosing a cheaper item than the allowance should produce a credit, recorded the same way as an extra, with the new contract total shown.